The latest
The on-site works for the Twentyfirst Street Bridge Replacement project have commenced.
BMD Constructions officially mobilised to the site on in October.
The demolition of the damaged bridge has begun.
The Twentyfirst Street Bridge replacement has truly kicked into gear after delays impacted progress, particularly in obtaining critical river flow design data.
Despite the setbacks, the project is still targeting a completion date of mid-2025.
Additional works will also be carried out in the Bookmark Creek area by the Department of Environment and Water (DEW), which will deliver significant environmental benefits to the area.
To read about DEWs exciting project visit here.
Twentyfirst Street Bridge Demolition
Twentyfirst Street Bridge Replacement
There will be no pedestrian access for the duration of the project from Monday 30 September.
Council has been successful in securing funding for the detailed design of the bridge replacement and is investigating other avenues of funding to support the construction of the bridge.
The project will also receive disaster recovery funding.
Further details of the costs involved will be provided to the community as the project progresses.
In March 2022 (pre Flood), a regular engineering assessment of the bridge was undertaken by TMK Engineering and whilst it was not in excellent condition at that time and required some remediation works, it was determined safe to use.
After the 2022 River Murray Flood, all major Council assets that were flood affected had to be assessed by an engineer prior to re-opening. TMK Engineering returned in March 2023 (post-flood) and undertook another engineering assessment, which then determined that due to damage sustained through the flood, it was no longer safe to use. This report also identified that the damage incurred was significant and the costs to remediate the bridge structure are likely comparable to replacing the bridge structure entirely.
Upon receiving this report which confirmed that the bridge was not safe to be reopened, Council couldn’t risk the public’s safety and made the decision to close the bridge to all users.
After the determination to close the bridge, Council engaged the services of Tonkin Consulting to undertake a design and options report for a replacement bridge. This scope of work also included a secondary condition assessment on the bridge structure and road approaches.
In August 2023, Tonkin Consulting completed a Level 3 Bridge Inspection to investigate the potential short term temporary reopening of the bridge and to what type of users. This inspection identified that the Twentyfirst Street Bridge could be reopened to pedestrians and cyclists only if several access controls were implemented. Following the implementation of the access controls the bridge was reopened to pedestrians and cyclists with access to remain in place until construction commences.
In addition to the Level 3 Bridge Inspection, Tonkin Consulting also completed a Condition Assessment and Options Investigation Report which provided Council with six (6) design options for the permanent replacement of the bridge. The option selected is the most cost effective and will ensure the construction of a resilient asset that will be able to withstand future flooding events.
Further, two rounds of geotechnical drilling – which involves drilling down 15metres against the bridge abutments – were completed in late 2023. The results of the geotechnically drilling have ensured that the design is catered to the specific soil and site conditions.
In 2022, the Twentyfirst Street Bridge was inundated with floodwaters and closed to the public for safety reasons.
After the water receded, extensive engineering assessments concluded that the bridge needed to be replaced in its entirety.
Following a competitive tender process, Council has appointed experienced civil contractors, BMD Constructions as the preferred contractor to construct the new Twentyfirst Street Bridge after it was damaged during the River Murray Flood in 2022.
Council has considered a number of design options for the replacement of the Twentyfirst Street Bridge and has selected the design option that will address impediment to flow, provide road and pedestrian user improvements, provide a high level of flood immunity and water flow constraint reduction and is costed within a range that is affordable with funding assistance from the State and Federal Governments.
While Council understands the frustrations of the local community surrounding the closure time, protecting the safety of our community has always been Council’s highest priority.
It has been extremely important to ensure the works on the bridge were not a ‘quick fix’ and that the bridge would serve as a long-term solution which would be safe and resilient well into the future.
On-site works at the bridge are expected to commence in August 2024 by BMD Constructions who will employ seven local sub-contractors to assist with the project. The project is anticipated to be complete by mid-2025.